Curb and Gutter Placement and Sidewalk Preparation Progressing
Work Completed This Week
The contractor continued saw cutting along the south side of 16th Street and completed sidewalk and curb and gutter removal between Kenilworth Avenue and Grove Avenue. Excavation and aggregate base placement for sidewalk and curb and gutter were completed between Clinton Avenue and Kenilworth Avenue.
The contractor formed and poured curb and gutter between Maple Avenue and the southwest corner of Kenilworth Avenue. Work remains at Wenonah Avenue and at gaps in the curb line where frames and grates require adjustment.
Work Anticipated Next Week
Installation and activation of the temporary traffic signals are expected to be completed. Forming and pouring of sidewalk along the south side of 16th Street between Harlem Avenue and Kenilworth Avenue are anticipated. Frame and grate adjustments in the curb line are scheduled to be completed, and combined sewer point repairs are planned to begin along 16th Street, starting at Harlem Avenue.
Neighborhood Impacts
No parking restrictions are in effect along the south side of 16th Street between Harlem Avenue and Clarence Avenue from 7:00 a.m. to 4:00 p.m., Monday through Friday. The south-side parking lane between Harlem Avenue and Kenilworth Avenue is closed to parking.
Residents and drivers should watch for construction signage, follow posted parking restrictions and traffic control measures, and use caution near workers and equipment. Visit this website for weekly updates throughout the project.