Temporary Traffic Signal Installation and Removal Preparation
Work Completed This Week
The contractor began installing temporary traffic signals, installed tree protection, and completed tree root pruning throughout the project limits. Saw cutting for curb and gutter and pavement removal was completed along the south side of 16th Street between Harlem Avenue and Wenonah Avenue.
Work Anticipated Next Week
Installation of the temporary traffic signals is expected to be completed. Saw cutting for removals along the south side of 16th Street between Harlem Avenue and Kenilworth Avenue is anticipated to finish, with removals scheduled to begin along the south side of the roadway.
Neighborhood Impacts
No parking restrictions are in effect along 16th Street between Harlem Avenue and Kenilworth Avenue from 7:00 a.m. to 4:00 p.m., Monday through Friday. Residents and drivers should watch for construction signage, follow posted parking restrictions and traffic control measures, and use caution near workers and equipment. Visit this website for weekly updates throughout the project.